Ingit Anand, Vinod Patel, Namrata Vaja and Pratik Doshi set out how Ahmedabad and GIFT City have diverged on façade regulation, and where the costs that go unbudgeted sit: cleaning access, maintenance and a consultant appointed far too late.

Pull quotes from the discussion, quoting Vinod Patel, Ingit Anand, Namrata Vaja and Pratik Doshi
Quoted from the discussion.

Ahmedabad has joined the cities building upward, with schemes above 100 and 150 metres under construction, and Anand expects the next decade to stay bullish on a floor-space index newly raised to 5.4 for tall buildings, the Commonwealth Games and the bullet train. GIFT City is the concentrated pocket in that picture, holding a share of Gujarat's tall buildings out of all proportion to its size. What the two places do not share is a rulebook. Patel sets out the difference bluntly, starting from the fact that Ahmedabad already limits how much of an envelope may be glazed and that the limit is a dead letter.

Ahmedabad Municipal Corporation has a law in the GDCR: you cannot use glass façade for more than 50%. It is totally not followed by any builder or any architect in Ahmedabad. Every building is a glass box.

Vinod Patel, Trogon Group

Two codes for one city region

Buildings that ignore the limit are granted use permission anyway, and below 70 metres Patel notes there is no third-party review of the façade at all, which he argues should be introduced. The mechanics differ too, since GIFT requires the façade to be designed inside the given floor plate while Ahmedabad allows a two-foot projection for elevation, so one brief produces different envelopes either side of the boundary. His conclusion is that the codes should be brought level, since the alternative is a region where compliance depends on which authority is looking. Anand, whose projects sit in GIFT, describes the opposite trajectory from the developer's side.

When we started our project in 2021, façade was just one component of the building. There was no peer review system for the façade design. Now GIFT has mandated the peer review.

Ingit Anand, Collated Ventures

He reads that as an improvement rather than an obstacle, and says the same of a fire department that defines its approvals from development plan through to occupancy and then audits the building periodically. Patel's objection to the glass box is not aesthetic either. Ahmedabad is hot and dusty, and his practice runs a sun-path study across every season before settling orientation, glass specification, insulation and thermal conductivity, which on residential work means glazing the north and east rather than wrapping the whole mass.

The costs that never reach the budget

Anand is emphatic that a façade cannot be budgeted as a percentage of project cost. His organisation works from benchmark data, pricing the components of a single exploded panel to reach a rate per square foot of glazing area rather than built-up area, since basements inflate the latter and carry no envelope. Inflation and a provision for the unforeseeable go on top, and he offers his current project as the illustration: aluminium stood at 275 to 280 rupees when the design was budgeted and 385 by the time the tender was awarded. Patel adds the cost most often left out altogether, since the access and cleaning system on one of his buildings came to around a crore and belongs inside the building's cost rather than beside it.

Appointed too late to help

Vaja, who sees these projects from the client's side, puts the failure at a specific moment: the façade consultant is engaged once design development and tendering are finished and the frame is rising, when opinions are sought but the decisions have been taken. Her example is post-tensioned slabs: the façade contractor arrives ten or twelve floors in, points out that anchors cannot be drilled into a PT slab, and the remedy becomes rebar and a cast upstand where a cast-in channel would have settled it on paper. Walls that miss the mullion line are the same failure in another form, visible from outside as a wall standing in the glazing.

Façade is not a finishing item. For high-rises it is part of our shell and core structure.

Namrata Vaja, Technical Entrepreneur Agile Management

Her sequence is that the consultant joins when the architectural concept is frozen and before schematic design begins, and that the vendor is appointed by the time the frame reaches ground level, since three or four basements take six or seven months and that is time enough to choose one properly. She adds a point about how progress is judged: the pre-construction work runs six or seven months, so installation speed should be counted from the first panel, not from the day the contractor signed. Anand puts it as a straight line: every month of delay adds design, engineering and cost, and he would place the façade inside architectural design rather than alongside it.

Tested where it matters, maintained after everyone leaves

Doshi draws the testing line by risk rather than by rule. A rectangular building under 70 metres carries about 1.8 kilopascals of wind load against systems tested to 3.5 negative, so a performance mockup adds little beyond a corner test on site, though where regulation demands one it is honoured. A complex envelope is another matter, and he is candid that a project delivered a decade ago with an awkward corner and no mockup survived on the strength of its design team rather than its process. He would test one now. The value he weighs most is the rehearsal rather than the certificate, since the fabricator's team and the system team learn together where air leaks and why. On site the controls are frequent audits and repeated training, strictest over the first hundred panels and undone regularly by staff changing at the fabricator.

We kept one engineer in the fabricator's factory and one on site. It was so clinical that the customer said he had not seen a project like this, and it cost us around 50 lakh.

Pratik Doshi, Schüco India

Which leaves the question Anand keeps returning to, and which nobody in the region has answered. A developer's obligation ends two or three years after handover, and a tower of 150 metres then passes to owners who must run pressurisation, lifts, waste and the façade itself in a dusty climate. His argument is that height does not define development, since infrastructure comes first and real estate second, and the threshold worth finding is the one the city can maintain.

Synthesis based on the panel discussion, moderated by Mitul Gajjar (Façade Engineering Services), with Namrata Vaja (Technical Entrepreneur Agile Management), Ingit Anand (Collated Ventures), Pratik Doshi (Schüco India) and Vinod Patel (Trogon Group) at Zak World of Façades Ahmedabad, 17 April 2026. Watch the full recording via the link above.